Newtown Township 2026 Liquid Fuels Road Program
Bid Details, Scope, and Road List
Sealed bids due March 18, 2026 at 10:00 AM (PennBid); public opening at Remington & Vernick Engineers in Yardley.
Newtown Township has issued bid details for the 2026 Liquid Fuels Road Program, an annual infrastructure investment focused on proactive road rehabilitation—going beyond simple resurfacing to address structural repairs, drainage, and accessibility improvements.
Bid Submission & Public Opening

- Submission Method: Electronic bidding via PennBid
- Submission Date: February 24, 2026
- Submission Deadline: March 18, 2026 (prior to) 10:00 AM EST
- Public Bid Opening: March 18, 2026 at 10:00 AM EST
- Location: Remington & Vernick Engineers, 1010 Stony Hill Road, Suite 175, Yardley, PA 19067
- Public Attendance: The public may attend the opening of bids
Program Scope: What’s Included
The 2026 program includes a package of roadway improvements designed to improve safety, extend pavement life, and strengthen stormwater performance.
- Infrastructure replacement: concrete curbs, sidewalks, and depressed driveway aprons
- ADA accessibility: ADA-compliant curb ramps with detectable warning surfaces and concrete cheek walls (as needed)
- Drainage improvements: replacement of inlet tops, frames, and grates
- Pavement restoration: base repairs, 1.5-inch asphalt milling, then a new 1.5-inch wearing course
- High-visibility markings: fog lines, double yellow, dashed dividers, and white hot thermoplastic legends (e.g., “Left” and “ONLY”)
The bid details emphasize that prioritizing sub-surface drainage and base repairs helps prevent premature potholing and extends the life cycle of the asphalt wearing course.
Road Locations: Base Bid and Alternate Bids
Roadway segments were selected through a data-driven process and are divided into a Base Bid (high-priority) and Alternate Bids that may be awarded depending on funding outcomes.
The bid details describe the 2026 program as revitalizing approximately 1.85 miles of roadway (1.54 miles Base Bid and 0.31 miles Alternate Bids), combining drainage upgrades, ADA accessibility, and pavement restoration to support a safer and more resilient transportation network.
| Category | Roadway Location | Specific Limits / Scope |
|---|---|---|
| Base Bid | Eagleton Farm Road | Back loop starting at Millers Road intersection |
| Base Bid | Union Street | Entire length |
| Base Bid | Jonquil Drive | Eagle Road to Shamrock Court |
| Base Bid | Everett Drive | House 101 to Lower Dolington Road |
| Base Bid | Columbine Circle & Goldenrod Court | 14 Columbine Circle to South Drive |
| Base Bid | Hidden Valley Lane | Entire length |
| Base Bid | N. & S. Sycamore Street | Entire length (Pavement Markings Only) |
| Alternate Bid | Wrights Road | Entire length (Type 2 Repairs* Only) |
| Alternate Bid | Linton Hill Road | Entire length (Type 2 Repairs* Only) |
| Alternate Bid | Westwood Court | Entire length |
| Alternate Bid | Oak Court | Entire length |
| Alternate Bid | Brentwood Court | Entire length |
| Alternate Bid | Briarwood Court | Entire length |
Source: 2026 Liquid Fuels Road Program Bid Details


Budget & Funding
- Total budgeted amount: $850,000
- Base Bid estimated cost: $698,000
- Alternate Bids estimated cost: $237,000
The program funding is described as a split between the Highway Aid Fund and the General Fund, with an emphasis on maximizing Liquid Fuels (Highway Aid) dollars to protect local tax dollars for other services.
Because the project is funded in part by the PennDOT Municipal Liquid Fuels Program, materials and construction methods must meet PennDOT specifications.